President Avenue Pump Station

Project Info
  • Construction Date: September 2019 to January 2020
  • Location: Fall River MA
  • Category: Cofferdam
  • President Avenue Pump Station :
Project Details

In 2019 NSI installed a cofferdam for a new sewer pump station in Fall River. The 32’x32’x26’ coffer dam used 2 levels of bracing and 35’ PZ22 sheet piles. High groundwater levels and the new configuration required 2 hydraulic beams to promote the installation and beam removal once the station was completed.